|
|

|
| Summer 1996 Issue |
Why Competitive Bidding Doesn't Guarantee
the Lowest Price
Conventional wisdom holds that the only way to get the lowest
price on a building project is to get competitive bids from
several general contractors. This isn't necessarily so, and
here is why.
Let's say you have chosen a design professional to prepare
the plans and specifications for your new building and are
ready to select a constructor for the project. Two principal
options are avalable at this point.
The Two Options
You can select several qualified general contractors to submit
fixed-price bids, awarding the contract to the lowest bidder.
Or you can select the single most qualified construction company
and negotiate a contract. This contract may be on a "Cost
Plus Fee" basis, which means the general contractor's
compensation is agreed upon before construction begins, and
you pay the actual cost for the construction work.
The "Cost Plus" contract may have a Guaranteed Maximum
Price provision, where the general contractor commits to completing
the project at or below a mutually agreeable price, with any
savings shared by owner and contractor on pre-arranged terms.
The Role of Sub-Contractors
While a general contractor handles some of the work with its
own employees - the concrete and carpentry work, for example
the G.C. contracts with other firms for work involving specialized
skills: electrical work, plumbing, heating and air conditioning,
painting, lighting, and interior design, for example. These
subcontractors, frequently account for 60% to 70% of the value
of the work.
The reason for using such specialty companies is obvious.
It would take massive resources to maintain active crews with
all the varied talents required for a building project. Fixed
costs and financial risks are reduced by subcontracting.
Prices from Competing G.C.s
Competition requires that a general contractor get bids from
each of the subcontract trades to put together, hopefully,
the lowest possible total bid package. Each general contractor
has its own preferred subcontractors it will invite to submit
bids. It would be the sheerest of coincidences for a single
general contractor to receive all the lowest bids (indicated
by the shaded areas in the accompanying tables) from the group
of bidding subcontractors. In this case, the award will probably
go to general contractor "A", whose total combination
of subcontractor bids is the lowest at $1,569,500.
| Competitive Bid Pricing |
| |
General Contractor |
| Subcontractors |
A |
B |
C |
| Structural Framing |
$420,000 |
$490,000 |
$510,000 |
| Electrical |
$230,000 |
$190,000 |
$225,000 |
| Plumbing |
$160,000 |
$187,500 |
$154,000 |
| Heating |
$405,000 |
$463,500 |
$420,000 |
| Painting |
$118,000 |
$107,500 |
$ 95,000 |
| Masonry |
$236,500 |
$229,000 |
$187,500 |
| Total |
$1,569,500 |
$1,660,750 |
$1,591,500 |
Prices from a Favored G.C.
Now let's look at an alterate solution. What can happen if
an owner decides to go with a single, particularly well-qualified
building firm on a negotiated contract basis? In addition
to the benefits of working with a single firm from the start
of the project, the client can get the lowest subcontract
prices.
In this example, assume that the same subcontractor bids are
available to constructor "X", who has been selected
as the general contractor or construction manager. Because
he is not involved in competitive bidding against other G.C.s,
he can attract and select the best available bids (again,
those shaded boxes). As a result, he is able to put together
a price package totaling $1,451,500 which, in our oversimplified
example, is $118,000 under the lowest total price received
through traditional bidding.
| Negotiated Contract
Pricing |
| Subcontractors |
Builder
X |
|
|
| Structural Framing |
$420,000 |
$490,000 |
$510,000 |
| Electrical |
$190,000 |
$230,000 |
$225,000 |
| Plumbing |
$154,000 |
$187,500 |
$160,000 |
| Heating |
$405,000 |
$463,500 |
$420,000 |
| Painting |
$ 95,000 |
$118,000 |
$107,500 |
| Masonry |
$187,500 |
$236,500 |
$229,000 |
| Total |
$1,451,500 |
$1,725,500 |
$1,651,500 |
Of course, a negotiated contract with any single building
firm does not automatically assure a client of the lowest
final price. One key lies in selecting the right construction
firm, one of proven experience and excellence of reputation.
Another key is using the firm's knowledge and experience throughout
the planning and design process.
In many cases, a client is reluctant to put a project into
the hands of even the most reputable builder, on a single-source-of-responsibility
basis. He has too long been a victim of the concept that the
way to obtain the lowest possible price is to get as many
competitive, fixed-price bids as he can. But, as we've shown,
competitive bidding, by nature, doesn't always guarantee a
client the lowest price for a project.
|