Many
people are familiar with the services delivered by a general
contractor, but may be unfamiliar with those of a construction
manager. An overview of services delivered by both project
delivery methods follows, broken down into each phase of the
project from planning through completion.
Project
Phase
|
Description of Service |
General Contractor |
Construction Manager
At- Risk |
 |
| 1) |
Selected based on ability |
|
|
 |
| 2) |
Team approach between architect and
contractor |
|
|
 |
| 3) |
Construction schedule and project
phasing planning |
|
|
 |
| 4) |
Single contract for construction services |
|
 |
 |
 |
| 1) |
Construction expertise during design
phase |
|
|
 |
| 2) |
Cost input and value management during
design |
|
|
 |
| 3) |
Allows fast-track construction |
|
|
 |
| |
|
 |
| 5) |
Permits tax exempt/direct purchase
program |
|
|
 |
| 6) |
Formal progress reports to project
decision-makers |
|
|
 |
| 7) |
Evaluation of alternative building
systems and components |
|
|
 |
 |
| 1) |
Management of trade contractor bidding |
|
|
 |
| 2) |
Bid “open book”; cost
savings shared with owner |
|
|
 |
| 3) |
Ability to competitively bid project |
|
 |
 |
 |
| 1) |
Only pay for actual cost of work,
owner benefits from cost savings |
|
|
 |
| 2) |
Responsible for on-site general requirements |
|
 |
 |
| 3) |
Guarantee of construction cost |
|
 |
 |
| 4) |
Guarantee of schedule and completion
dates |
|
 |
 |
| 5) |
Complete responsibility of performance
and payment of trade contractors |
|
 |
 |
| 6) |
Responsibility and direct control
over all trade contractors for site activities |
|
 |
 |
| 7) |
Perform work with own forces |
|
 |
 |
 |
| 1) |
Single source responsibility for warranty/call-back
issues |
|
 |
 |
| 2) |
11-month walk-through to correct all
potential warranty issues
|
|
 |
 |